| Location | Bátonyterenye |
| Function | industrial hall |
| Floor area | 1250 m² |
| Client | F3R-Technológia |
| Scope of project | building permit and construction plans |
| Year of design | 2010-2013 |
| Status | completed |
| Lead designer | TH-Stúdió |
| Architects | György Hidasi, Csilla Dubniczki, Katalin Kersner, Zoltán Vass |
| Contractor | Market |
| Structural engineering | Gyuris 2000 |
| MEP engineering | Körös Consult |
| Electrical engineering | Yurosignal, Provill |
| Utility networks | Körös Consult, FL-Gáz, Bau-Kvalitás |
| Road engineering | C-terv |
| Environment protection | Varsoft |
The Client intended to establish a sprinkler pipe prefabrication plant on their standalone site. The facility is designed to support the manufacturing process that prepares pipe networks for automatic water-based fire suppression systems (sprinklers) to be installed in various buildings. The production follows a detailed technological specification to enable on-site assembly of the sprinkler pipe networks.